Facade Replacement Works: Building 33 Fortnightly Lookahead

11 Sep 2023

The Building 33 cladding replacement works are continuing. The notification below provides a fortnightly lookahead for upcoming works.

This cladding project is expected to run from April 2023 until November 2023

Fortnight Lookahead: 11 September 2023 to 25 September 2023

Affected Area & Disruption

Time

Date

North & South Elevation:

  • Removal of cladding, installation of sub framing and installation of new panels continues. This will be noisy works.
  • EWP and other machinery will be used, creating noise.

Refer to Figure 2 below.

Note: Access to Brew point Café will remain open during normal operating hours. Construction works on the North and South elevations of the building only to commence after 11am.

07:00am – 05:00pm

Expected works until end of September

West Elevation (Entry):

  • Removal of cladding, installation of subframing and installation of new panels continues. This will be noisy works.
  • Structural issue identified with substructure above entry will require extended closure to this area.
  • Some disruption to main entrance on Union Road, this will include half of the entrance foyer being closed at any one time as contractor removes panels and installs new. These works are expected to create noise.
  • Additional site fencing installed along pathway adjacent to Union Road.

NOTE: The viewing room remains accessible at all times.

07:00am – 05:00pm

Expected works until early November

Building 33 Lift:

  • There will be intermittent lift closures during working hours with alternative pedestrian routes in place (Refer to Figure 3 below).

07:00am – 05:00pm

04/09/23 – 16/10/23

Figure 1 - Site Layout Plan:

 

 

Figure 2 - Site works:

 

Figure 3 – Lift Closure:

 

 

Project details

 

Building 33 Façade Replacement Project. Refer to the Façade Replacement Program website for more information.

 

Contact

Johnny Hegerty, Principal Project Officer:

We apologise for the inconvenience this may cause and thank you for your understanding during this time.

Return to Road and Building works