The Centre for Advanced Imaging (57) forms part of the UQ Façade Replacement Program. As part of these works the cladding on the CAI building will be replaced.
The Contractor has established work areas at the CAI Building in recent weeks and will continue to undertake preparation activities in readiness for the main cladding replacement works. This notification provides a lookahead for the upcoming fortnight.
The cladding works to CAI are expected to continue until August 2024.
Affected Area & Disruption | Time | Date |
CAI Laneway
| All Day | 29/08/23 to 5/09/23 |
CAI Laneway - Rooms 132, 133, 134, 135, 136 and 137.
| 6:30am to 4:00pm | 31/08/23 to 1/09/23 |
Richie Building East Elevation – Contractor Compound
| 7am-1pm | 2/09/23 |
Work details
St Lucia West Package – Centre for Advanced Imaging Façade Replacement. Refer to the Façade Replacement Program webpage for more information.
Project details
St Lucia (West Package) cladding replacement project.
Contact
Mel Marke, Associate Director (Infrastructure):
- Call: 0429 885 361
- Email: m.marke@uq.edu.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.