Facade Replacement Works: Hawken Engineering Building (50) lookahead

29 Sep 2023

The Hawken Engineering Building (50) cladding replacement works are underway.

The notification below provides a lookahead for upcoming works.

Affected Area & Disruption

Time

Date

  • Contractor removing cladding to North and South of Building, EWPs will be used in areas where cladding is to be removed; please refer to Figure 1 below marked “stage 1” for cladding locations.
  • disconnection of services may be required.
  • Hawken laneway to be closed during EWP operations (access to Lab S105 maintained)
  • Internal access to areas may be required during removal and installations so some disruption will occur.
  • Noisy works are expected.

Footpath may have intermittent closures, alternative pedestrian routes to be put in place.

Bicycle stands located North side of Hawken will be closed.

Motorcycle Parking East of Hawken will be closed.

6:30am – 05:00pm

Please note that these works will be undertaken on the following dates only.

  • Saturday 30/09/2023

  • Saturday 07/10/2023

  • Saturday 14/10/2023

  • Saturday 21/10/202

  • Saturday 28/10/2023

Figure 1

Work details

These works form part of the Façade Replacement Program and more information about this program can be found here.

Project details

 

St Lucia (East Package) cladding replacement project.

Contact

Johnny Hegerty, Principal Project Officer:

We apologise for the inconvenience this may cause and thank you for your understanding during this time.