The Physiology Lecture Theatres (63) forms part of the UQ Façade Replacement Program. As part of these works the cladding on the Physiology building will be replaced.
This notification provides a high-level look ahead of works scheduled for the coming months. Ongoing communications will be issued throughout the works period to notify users of and around this building of any expected disruptive works.
Works at Physiology Lecture Theatres (63) are expected to run from October 2023 to August 2024.
Affected Area & Disruption | Time | Date |
Physiology Lecture Theatres |
|
|
External Lift - Site Setup of Fencing and Hoarding / Scaffold Build
- Lift out of commission during scaffold build for safety of users. Alternate access via Southern Entry with Ramp.
- Exclusion Zones around works areas for safety of users may impact usual pedestrian pathways.
- Noisy Works during scaffold build limited to material and machine movements.
- Removal of existing cladding and framing, and installation of new cladding and framing
- Exclusion Zones around works areas for safety of users may impact usual pedestrian pathways.
- Noisy Works during cladding replacement will include cutting and drilling equipment. Block out periods communicated by Stakeholders have been established with the Contractor.
- Removal of Scaffold
- Lift out of commission during scaffold build for safety of users. Alternate access via opposite entry.
- Exclusion Zones around works areas for safety of users may impact usual pedestrian pathways.
- Noisy Works during scaffold removal limited to material and machine movements.
|
All Day - 7am to 5pm
All Day 7am to 5pm
All Day 7am to 5pm
|
30/10/23 to 20/11/23
21/11/23 to 25/01/24
29/01/24 to 31/01/24 |
Northern Entry - Site Setup of Fencing and Hoarding / Scaffold Build
- North Entry door Closed during scaffold build for safety of users. Alternate access via Southern Entry with Ramp.
- Exclusion Zones around works areas for safety of users may impact usual pedestrian pathways.
- Noisy Works during scaffold build limited to material and machine movements.
- Removal of existing cladding and framing, and installation of new cladding and framing
- Exclusion Zones around works areas for safety of users may impact usual pedestrian pathways.
- Noisy Works during cladding replacement will include cutting and drilling equipment. Block out periods communicated by Stakeholders have been established with the Contractor.
- Removal of Scaffold
- Exclusion Zones around works areas for safety of users may impact usual pedestrian pathways.
- Noisy Works during scaffold removal limited to material and machine movements.
|
All Day - 7am to 5pm All Day – 7am to 5pm
All Day 7am to 5pm
All Day 7am to 5pm
|
30/10/23 to 30/10/23
31/10/23 to 20/11/23
21/11/23 to 19/01/24
22/01/24 to 24/01/24 |
Southern Entry - Site Setup of Fencing and Hoarding / Scaffold Build
- South Entry door Closed during scaffold build for safety of users. Alternate access via North Entry.
- Exclusion Zones around works areas for safety of users may impact usual pedestrian pathways.
- Noisy Works during scaffold build limited to material and machine movements.
- Removal of existing cladding and framing, and installation of new cladding and framing
- Exclusion Zones around works areas for safety of users may impact usual pedestrian pathways.
- Noisy Works during cladding replacement will include cutting and drilling equipment. Block out periods communicated by Stakeholders have been established with the Contractor.
- Removal of Scaffold
- Exclusion Zones around works areas for safety of users may impact usual pedestrian pathways.
- Noisy Works during scaffold removal limited to material and machine movements.
|
All Day - 7am to 5pm All Day – 7am to 5pm
All Day 7am to 5pm
All Day 7am to 5pm
|
30/10/23 to 30/10/23
31/10/23 to 23/11/23
24/11/23 to 16/01/24
17/01/24 to 19/01/24 |
Ramp Balustrade - Site Setup of Fencing and Hoarding / Scaffold Build
- South entry Ramp Closed during scaffold build for safety of users. Alternate access via North Entry.
- Exclusion Zones around works areas for safety of users may impact usual pedestrian pathways.
- Noisy Works during scaffold build limited to material and machine movements.
- Removal of existing cladding and framing, and installation of new cladding and framing
- During Ramp works access to ramp will be closed for safety of users. Alternate access via North Entry.
- Exclusion Zones around works areas for safety of users may impact usual pedestrian pathways.
- Noisy Works during cladding replacement will include cutting and drilling equipment. Block out periods communicated by Stakeholders have been established with the Contractor.
- Removal of Scaffold
- Ramp access Closed during scaffold removal for safety of users. Alternate access via North Entry.
- Exclusion Zones around works areas for safety of users may impact usual pedestrian pathways.
- Noisy Works during scaffold removal limited to material and machine movements.
|
All Day - 7am to 5pm All Day - 7am to 5pm
All Day 7am to 5pm
All Day 7am to 5pm
|
29/05/24 to 18/06/24
30/05/24 to 18/06/24
19/06/24 to 22/07/24
23/07/24 to 23/07/24 |
Figure 1: Physiology Lecture Theatres Cladding Replacement Overall Site Plan
Figure 2: Lift, North and South Entry Staging
Figure 3: South Entry Ramp Entry Staging
Figure 4: Affected doorways during North Entry Stage
Figure 5: Affected doorways during South Entry and Ramp Stage
Work details
St Lucia West Package Cladding Replacement. Refer to the Façade Replacement Program webpage for more information.
Project details
St Lucia (West Package) cladding replacement project.
Contact
Mel Marke, Associate Director (Infrastructure):