Facade Replacement Works: Otto Hirschfeld (81) lookahead

20 Nov 2023

Otto Hirschfeld (81) forms part of the UQ Façade Replacement Program. As part of these works the cladding on the Otto Hirschfeld building will be replaced.

This notification provides a high-level look ahead of works scheduled for the coming fortnight. Ongoing communications will be issued throughout the works period to notify users of and around this building of any expected disruptive works.

Works at Otto Hirschfeld Building are expected to run from October 2023 to March 2024.


Forecast Timeframe: 20 November 2023 – 01 December 2023

Affected Area & Disruption

Time

Date

Otto Hirschfeld Building

Main Entry

  • Remove Caulking, cladding and tophats
    • Exclusion Zones around works areas for safety of users may impact usual pedestrian pathways.
    • Noisy Works including cutting and drilling and machine movements.

All Day - 7am to 5pm

20/11/23 to 8/12/24

Anatomy Entry

  • Scaffold Setup / Remove existing Soffit / remove existing Caulking
    • Exclusion Zones around works areas for safety of users may impact usual pedestrian pathways.
    • Noisy Works including cutting and drilling and machine movements.

 

All Day - 7am to 5pm

27/11/23 to 15/12/23

Figure 1: Otto Main Entry Exclusion Zone Plan

Aerial view of a buildingDescription automatically generated

Figure 2: Affected doorways during Main Entry Works

A blue door with a red sign on itDescription automatically generated

Figure 3: Otto Exclusion Zones

A collage of a parking lotDescription automatically generated

Work details

St Lucia West Package Cladding Replacement.  Refer to the Façade Replacement Program webpage for more information.  

Project details

 

St Lucia (West Package) cladding replacement project.

Contact

Mel Marke, Associate Director (Infrastructure):

 

We apologise for the inconvenience this may cause and thank you for your understanding during this time.

Return to Road and Building works