Please be advised that glazing will be replaced at Sir James Foots Building (47A) from Hawken Lane.
Affected areas
When
- Start: Monday, 27 November 2023
- Finish: Wednesday, 29 November 2023
- Times: 6:00am to 5:00pm
Work details
- Monday 27 November, PM: Bollards will be droped off.
- Tuesday 28 November AM – Wednesday 29 November PM:
- Delivery of Small Boom Lift within delivery cut in on Staff House Road.
- Exclusion zone to be set up within Hawken Lane to complete north side of building works.
- 2 workers in EWP basket – 1 worker as spotter and pedestrian traffic control – 1 worker within classroom – SHAPE supervisor roaming between areas.
- Once northern side of building complete all workers to spot the transport of the EWP to the laneway behind SJF.
- Exclusion zone to be set up in SJF laneway.
- Identical setup for workers 2 in EWP – 1 worker as spotter – 1 worker inside room - SHAPE supervisor roaming between areas.
- Existing glass to be removed from site by contractor.
- When required EWP to be stored at the far end of Hawkn Lane or behind SJF – ensuring that the bin enclosure behind SJF is made available.
- EWP to be picked up from Staff House Road cut in.
Contact
Bradley Cox
- Call: +61 416 050 471
We apologise for the inconvenience this may cause and thank you for your understanding during this time.