Noisy Works: Otto Hirschfeld (81)

20 Nov 2023

There will be some noisy works in Otto Hirschfeld (81) levels 5, 6 and 7 to install new BMS control panels for the control of the air conditioning systems.

Affected areas

  • Otto Hirschfeld Plant Room 523
  • Otto Hirschfeld Plant Room 617
  • Otto Hirschfeld Plant Room 718
  • Otto Hirschfeld Level 5, 6 and 7 Corridors

When

  • Start: Tuesday, 21 November 2023
  • Finish: Thursday, 23 November 2023
  • Times: 6:00am to 4:00pm

Work details

There will be noisy works to mount some BMS panels on the walls of the plant room.
There will also be installation of comms cables along the corridors of levels 5, 6 and 7 to provide the BMS connectivity for the new panels.

Project details

The air conditioning controllers are past end of life and spare parts are no longer available.
The installation of the panels is in preparation for the new controllers which will be installed and commissioned in January 2024.

Contact

Neil Brown, Senior Building Systems Engineer:

We apologise for the inconvenience this may cause and thank you for your understanding during this time.