The Hawken cladding replacement works are ongoing and the notification below provides a lookahead for upcoming disruptive works.
The cladding replacement works to Hawken Building are only taking place during the semester holiday periods. It is expected works will be complete in June 2024.
Lookahead Timeframe: 8 January 2024 – 31 January 2024
Affected Area > Planned Works > Disruption | Time | Date |
All Areas
Access will remain to room S105 from Hawken laneway. | 6:30am – 5:00pm | 8 January 24 - Ongoing |
Figure 1: Hawken Works Update Plan
Project details
Hawken, St Lucia Cladding Replacement project. Refer to the Façade Replacement Program website for more information.
Contact
Casey Fredrickson, Senior Project Manager:
- Call: 0408 339 936
- Email: c.fredrickson@uq.edu.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.