The Hawken cladding replacement works are ongoing and the notification below provides a lookahead for upcoming disruptive works.

The cladding replacement works to Hawken Building are only taking place during the semester holiday periods. It is expected works will be complete in June 2024.

Lookahead Timeframe: 8 January 2024 – 31 January 2024

Affected Area > Planned Works > Disruption

Time

Date

All Areas

  • Works re-commencing 8 January.
    • Exclusion zones along southern laneway will be in place when EWP is operational.
    • Noise is expected in the form of EWPs and panel installation.
    • Intermittent pathway closures.
    • Some service disconnections / disruptions expected.

Access will remain to room S105 from Hawken laneway.

6:30am – 5:00pm

8 January 24 - Ongoing

Figure 1: Hawken Works Update Plan

Aerial view of a factoryDescription automatically generated

Project details

 

Hawken, St Lucia Cladding Replacement project. Refer to the Façade Replacement Program website for more information.

Contact

Casey Fredrickson, Senior Project Manager:

We apologise for the inconvenience this may cause and thank you for your understanding during this time.