There will be a disruption of electrical supply to the low voltage and 11kV supplies in Union, Schonell and central chiller precincts to allow for the installation of new 11kV switchgear at Sub 20 (Union).

Affected areas

Electrical supply interruption to the following areas

  • 0022 - All rooms
  • 0021A - All rooms
  • 0021B - All rooms
  • 0021C - All rooms
  • 0021D - All rooms
  • 0059A - 102, 103

Chilled water supply interruption to the following areas

  • Goddard (8) - All rooms
  • Parnell (7) - All rooms
  • Physics Annexe (6) - All rooms
  • Learning Innovation (17) - All rooms
  • Richards (5) - All rooms
  • Steele (3) - All rooms
  • Bio Sciences (94) - All rooms
  • Michie (9) - All rooms
  • Forgan Smith (1) - All rooms
  • Hartley Teakle (83) - All rooms
  • James and Mary Emelia Mayne Centre (11) - All rooms
  • Duhig Tower (2) - All rooms

When

  • Start: Monday, 29 January 2024
  • Finish: Monday, 29 January 2024
  • Times: 5:00am to 7:30am

Work details

Due to the complexity of isolation required with the Sub 20 RMU change over there will be some disruption to Union Precinct and central chiller electrical supply.
This disruption will also affect the central chilled water network for approximately 1 hour. Every effort will be made to ensure power disruptions are kept as short as possible.

Project details

The installation of new 11kV switchgear at Sub 20 will improve the safety of the electrical network as well as provide increased switching flexibility for future works.