Facade Replacement Works: Centre for Advanced Imaging (57), Gehrmann (60), Ritchie (64A) lookahead

1 Mar 2024

The Centre for Advanced Imaging, Gehrmann & Ritchie Research laboratories Buildings form part of the UQ Façade Replacement Program. The cladding replacement works are ongoing and the notification below provides a lookahead for upcoming disruptive works.

This CAI cladding works are expected to be complete in August 2024.

The Gehrmann cladding works are expected to be complete in October 2024

The Ritchie Research cladding works are expected to commence in April 2024 (Early measuring works taking place in March, refer below)

Lookahead Timeframe: 29 February 2024 – 15 March 2024

Affected Area & Disruption

Time

Date

Centre for Advanced Imaging

CAI East Elevation

  • Pedestrian Pathway Closure:
    • This pathway, refer Figure 2, will be closed during working hours from Monday 4th March.
    • The pathway will be opened in the event of an Emergency Evacuation from CAI. Alternative evacuation routes for other buildings will be signed.
    • The pathway will be opened after hours.
  • Deliveries lifted onto gantry above loading dock. Majority of these deliveries to be completed before 8:30am where possible

6am – 4pm

Duration of the Project

4/03/2024 – End of March

[End date TBC & other future closures to be communicated]

CAI Upper Roof

  • Cladding Replacement:
    • Expected completion is w/c 11th March.
    • Movement of materials on roof may cause noise on the floor below.
  • Scaffold Demob:
    • Removal of scaffold from the roof will commence once cladding to the roof is complete.
    • This may cause noise disruption to levels below.
    • A truck will be parked at the gantry for removal of scaffold materials.

6am – 5pm

Expected Completion w/c 11/03/2024

From ~ w/c 11/03/2024

CAI South Façade (Building Main Entry)

  • Building Entry:
    • Removal cladding and install new. Entry will be closed during this time. These works will take place on Saturdays.

6am – 5pm

Saturday Works

CAI North Elevation

  • Laneway between CAI and Gehrmann is closed for the duration of this project. Access only to services.
  • Cladding Replacement:
    • Cladding removal and installation of air seal, framing and new panels continues.
    • This may create noise.

-

6am – 5pm

Ongoing

Ongoing

CAI West Elevation

  • Scaffold has been removed, materials are stored and will be removed offsite over coming weeks.

-

-

Gehrmann Laboratories

Gehrmann South Elevation

  • Laneway between CAI and Gehrmann is closed for the duration of this project. Access only to services.

6am – 5pm

Ongoing

Gehrmann North Elevation

  • Front Entry Scaffold Build
    • Scaffold to be built adjacent the front entry to Gehrmann. This may create some noise.
    • Front entry will remain open.
    • Refer Figure 3.
  • Sunshade Removal Works:
    • Removal of sunshades to the north elevation to take place across these dates.
    • Research Rd will be closed to vehicles and pedestrians during this timeframe.
    • Pedestrian access will be restricted during this time.
    • Refer Figure 4 for more information.

6am – 12pm

6am – 5pm

6/03/2024

Saturday 9 March

Sunday 10 March

Monday 11 March [If Needed]

Ritchie Research Laboratories

Ritchie Research Block A & B South Elevation

  • Check measures being undertaken from a boom.
  • Research Road will be closed to vehicles during this timeframe.
  • Pedestrian access up Research Rd will be provided.
  • Refer Figure 4 for more information.

6am – 5pm

Monday 11 March

Tuesday 12 March Wednesday 13 March

Figure 1 – Building Layouts Reference

Figure 2 – CAI East Pathway Closure

A map of a assembly areaDescription automatically generated

Figure 3 – Gehrmann Front Entry Scaffold Build

Figure 4 – Gehrmann & Ritchie Works – Research Road Closure

Aerial view of buildings and roadsDescription automatically generated

Work details

St Lucia West Package – Centre for Advanced Imaging, Gehrmann Laboratories & Ritchie Research Laboratories Façade Replacement.  Refer to the Façade Replacement Program webpage for more information.  

Project details

 

St Lucia (West Package) cladding replacement project.

Contact

Casey Fredrickson, Senior Project Manager:

Latest