Please be advised of construction works in Plant Protection (8107)  to level 1 north wing and all of level 2. Works are required to remove asbestos from ceilings and vinyl flooring.

Lecture Theatre room 116 will remain in use through the work.

Affected areas

When

  • Start: Wednesday 8 March 2023
  • Finish: Friday 21 April 2023
  • Times: 6:30am to 3:00pm

Work details

  • Removal of asbestos, installation of new ceiling and floor coverings.
  • All works will be performed by licensed contractors.
  • Works will be conducted behind construction hoardings with air monitoring for safety compliance throughout the building.