Please be advised there will be a disruption of air conditioning to Therapies Annexe (84A) level 1, 2 and 6 to upgrade the air conditioning control system.
Affected areas
- Therapies Annexe (84A) levels 1, 2, and 6.
When
- Start: Tuesday, 11 April 2023
- Finish: Friday, 14 April 2023
- Times: 6.00am to 4.00pm
Work details
There will be periodic disruptions to the air conditioning due to power isolation and replacement of the controllers.
We will run air conditioning in manual with fixed cooling while the controls are swapped over
Project details
The air conditioning controls are past end of life and spare parts are no longer available.
The new controllers will be connected to the Building Management System which will improve scheduling, temperature monitoring and setpoint adjustment.
Contact
Neil Brown, Senior Building Systems Engineer:
- Call: 07 3346 1270
- Email: n.brown@pf.uq.edu.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.