Facade Replacement Works: Building 33 fortnightly lookahead

30 Jun 2023

The Building 33 cladding replacement works have commenced. The notification below provides a fortnightly lookahead for upcoming works. 

This cladding project is expected to run from April 2023 until November 2023 

Timeframe: 3 July 2023 – 17 July 2023 

Affected Area & Disruption 

Time 

Date 

 

  • Contractor removing cladding and decorative screes, EWP will be used in some areas where screens need to be removed. (Alternative pedestrian routes to be put in place) Noisy works expected. 

 

Note: Access to Brewpoint Café will remain open during normal operating hours. Construction works to commence after 11am. 

 

 

 

6:30am – 5:00pm 

 

 

 

 

 

3 July 2023 –  
17  July 2023 

 

 

​​Figure 1 Site Layout Plan:  

Figure 2 Impacts:  

Project details 

​​Building 33, St Lucia cladding replacement project. Refer to the Façade Replacement Program website for more information.​ 

Contact 

​​Johnny Hegerty​, ​Principal Project Officer​: 

We apologise for the inconvenience this may cause and thank you for your understanding during this time.