Facade Replacement Works: Mansergh Shaw (45) fortnightly lookahead

31 Jul 2023

The Mansergh Shaw (45) cladding replacement works have commenced. The notification below provides a fortnightly lookahead for upcoming works.

This cladding project is expected to run from July 2023 until July 2024

Timeframe: 31 July 2023 to 14 August 2023

Affected Area & Disruption

Time

Date

  • Contractor continuing to install scaffold to the Western side of Mansergh Shaw as per figure 1 below. Noisy works are expected.
  • Pedestrian access to West entry will be closed (open after hours) Alternative access via Staff House Rd.
  • Access for deliveries to the loading dock & gas storage area between Mansergh Shaw / Liveris will require communication to the project team.

06:30am – 05:00pm

31 July 2023 to
14 August 2023

Figure 1 Site Layout Plan


Project details

 

Mansergh Shaw, St Lucia cladding replacement project. Refer to the Façade Replacement Program website for more information.

Contact

Johnny Hegerty, Principal Project Officer:

We apologise for the inconvenience this may cause and thank you for your understanding during this time.

Return to Road and Building works

Latest