Facade Replacement Works: UQ Centre (27A) fortnightly lookahead

17 Jul 2023

The UQ Centre (27A) cladding replacement works are underway. The notification below provides a fortnightly lookahead for upcoming works.

This cladding project is expected to run from March 2023 until May 2024.

Timeframe:  17 July 2023 – 31 July 2023

Affected Area & Disruption

Time

Date

Western Elevation 

  • Cladding removal and structural works underway, noisy works expected.

  • Site Fence along Union Road to be in place for duration of project. Road will remain open.

6:30am – 5:00pm

For Duration of Project

17 July 2023 –
31 July 2023

Until May 2024

Eastern Elevation

  • Cladding removal and structural works underway, noisy works expected.
  • Lower walkway will be closed due to Upper-level scaffold build. alternative pedestrian route is located east and adjacent to existing walkways (Refer to Figure 2)

6:30am – 5:00pm

17 July 2023 –
31 July 2023

Northern Elevation

  • Cladding removal and structural works underway, noisy works expected.
  • Scaffold works progressing, noisy works expected.
  • Material Delivery and Hoist operations

6:30am – 5:00pm

17 July 2023 –
31 July 2023

Southern Elevation

  1. Cladding removal and structural works underway, noisy works expected.
  2. Access to Southeast corner will require EWP, Service Carpark to remain closed.
  3. Pedestrian bridge will be closed during EWP use. Alternative Pedestrian Route will be in place.

6:30am – 5:00pm

17 July 2023 –
31 July 2023

Figure 2 UQ Centre impacts

North impacts

West impacts

South impacts

Project details

 

UQ Centre, St Lucia cladding replacement project. Refer to the Façade Replacement Program website for more information.

Contact

Johnny Hegerty, Principal Project Officer:

We apologise for the inconvenience this may cause and thank you for your understanding during this time.

Return to Road and Building works

Latest