Please be advised there will be disruption to Forgan Smith (1) for roof repairs. Work is expected to take 2 to 3 weeks to complete.
Affected areas
- Forgan Smith (1) – East and West ends of the building
Works duration
- Start: Monday 24 July 2023
- Finish: Friday 11 August 2023
- Times: 6:00am to 5:00pm
Project details
- Installation of new roof flashings and ancillary items to repair roof leaks.
- During the initial setup of the site, both sides of the building will have exclusion areas established to ensure safety of pedestrians during the scaffolding erecting.
- Similarly, during the breakdown of the scaffolding, these exclusion areas will be established and removed where they are no longer needed.
- Contractors will be accessing numerous areas of Forgan Smith roof via an elevated work platform (EWP). Exclusion zones set up around the EWP while in operation.
- During the works, a small site compound on the grassed side will be needed to house materials, waste materials and the EWP access. This compound will be screened to avoid visual nuisance.
- No requirement for any rooms to be vacated.
Contact
Zak Williams
- Mobile: +61 466 655 377
- Email: z.williams@uq.edu.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.