We would like to inform you about the upcoming drainage works and turf replacement scheduled to take place at the Alumni Court at Patina Restaurant, St Lucia.
Affected Areas
Patina Restaurant Lawn – Alumni Court
When
Start: 16 September 2024
Finish: 27 September 2024
Times: 6am to 3pm
The lawn will return to full use from 14 October 2024.
Work details
Contractors and the UQ Grounds team will be working on site to remediate drainage followed by turf replacement. Patina will be open and operating as usual. Click here to find out more about Patina at Alumni Court.
Project details
The works will involve site set up, fencing, excavation of drainage trenches and connections to existing drainage
New drainage installation and gravel placement
Transfer of fill into lawn areas
Laying new turf
Clean-up of the lawn areas and surrounding stockpiling areas
Removal of fencing and reopen new lawn area on completion of works.
Accessibility and temporary disruptions
The ramp between the Great Court and Mansfield Place will be temporarily closed between 6am and 8am for the duration of the project and intermittently closed during the days to assist with loading and unloading.
The pedestrian walkway will also be closed for the duration of the project for safety reasons.
Appropriate signage will be in place for the duration of the project on site.
Access Patina’s through Cooper Road, (top of Cooper Road backing onto the Great Court)
We encourage pedestrians and wheelchair users to plan alternate travel routes to avoid delays and minimise the inconvenience caused. To access the accessibility map please click here.
Contact
Project Manager: Brad Mortimer
Call: PF Assist 07 3365 22 22
Email: pfassist@pf.uq.edu.au
We anticipate that these works will enhance the quality of our grounds and appreciate your understanding.
We apologise for the inconvenience this may cause and thank you for your understanding during this time.