Facade Replacement Works: Building 33 Fortnightly Lookahead

14 Aug 2023

The Building 33 cladding replacement works have commenced. The notification below provides a fortnightly lookahead for upcoming works.

This cladding project is expected to run from April 2023 until November 2023

Timeframe: 14 August 2023 to 28 August 2023

Affected Area & Disruption

Time

Date

  • Contractor removing cladding each side and decorative screens, EWP will be used in some areas where screens need to be removed. (Alternative pedestrian routes to be put in place), Noisy works expected.
  • Some disruption to main entrance on Union Road, this will include half of the entrance foyer being closed at any one time as contractor removes cladding.  Elevator and direct building entry to viewing room access still accessible.
  • Additional site fencing installed along pathway adjacent to union road. (Refer to figure 2 below) Services and club entry doors to be accessible when required. Pathway to remain open.
  • Some internal access may be required.

Note: Access to Brew point Café will remain open during normal operating hours. Construction works to commence after 11am.

11:00am – 05:00pm

14 August 2023 - 28 August 2023

Figure 1 Site Layout Plan:

Figure 2 Site works:

A aerial view of a buildingDescription automatically generated

Project details

 

Building 33, St Lucia cladding replacement project. Refer to the Façade Replacement Program website for more information.

Contact

Johnny Hegerty, Principal Project Officer:

We apologise for the inconvenience this may cause and thank you for your understanding during this time.