Please be advised there will be scheduled power shutdowns to allow for the installation of new Low Voltage infrastructure to reservoir pump house.

Affected areas

  • Main Reservoir (8273)

When

  • Start: Saturday 9 September 2023
  • Finish: Saturday 9 September 2023
  • Times: 6:00am to 12:00pm

Work details

Shut down #1 ‘Reservoir Pumps' will be isolated 6:00am - 6:30am (Approx 30mins interruption).

Due to water head tank, there will be no expected loss of water pressure throughout buildings. liaison has taken place with Urban utilities & P&F Plumber

Shut Down #2 'Sewage Pumps' will be isolated 6:30am - 10:30am (Approx 4hr interruption) liaison has taken place with P&F Plumber (Mike)

Shut Down #3' Reservoir Pumps' 11:30am - 12:00pm (Approx 30mins interruption). Due to water head tank, there will be no expected loss of water pressure throughout buildings. liaison has taken place with Urban utilities & P&F Plumber
Job Number: QCO-0012408

Contacts

James Tindall

Luke Cahill

We apologise for the inconvenience this may cause and thank you for your understanding during this time.