Facade Replacement Works: Mansergh Shaw (45) fortnightly lookahead

18 Oct 2023

The Mansergh Shaw (45) cladding replacement works are continuing with all cladding demolition now complete. The notification below provides a fortnightly lookahead for upcoming works.

This cladding project is expected to run from July 2023 until July 2024.

Timeframe: 16 October 2023 to 30 October 2023 

Affected Area & Disruption

Time

Date

North, West, South and East Elevation

  • Cladding air seal and sub-framing to walls.
  • This may create some noisy works, particularly for Level 4 & 5.
  • Deliveries to the compound area off Cooper Rd will continue.

06:30am – 05:00pm

Ongoing

Figure 1: Site Layout Plan:

Figure 2: Site Works Details:

Project details

 

Mansergh Shaw cladding replacement project. Refer to the Façade Replacement Program website for more information.

Contact

Johnny Hegerty, Principal Project Officer:

We apologise for the inconvenience this may cause and thank you for your understanding during this time.