The Mansergh Shaw (45) cladding replacement works are continuing with all cladding demolition now complete. The notification below provides a fortnightly lookahead for upcoming works.
This cladding project is expected to run from July 2023 until July 2024.
Timeframe: 16 October 2023 to 30 October 2023
Affected Area & Disruption | Time | Date |
North, West, South and East Elevation
| 06:30am – 05:00pm | Ongoing |
Figure 1: Site Layout Plan:
Figure 2: Site Works Details:
Project details
Mansergh Shaw cladding replacement project. Refer to the Façade Replacement Program website for more information.
Contact
Johnny Hegerty, Principal Project Officer:
- Call: 0459 979 518
- Email: j.hegerty@uq.edu.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.