Level 4 SBMS PC2 Laboratory Refurbishment Project: Otto Hirschfeld (81)

22 Nov 2023

There will be refurbishment work to Level 4 in Otto Hirschfeld (81) to allow for the delivery of a new PC2 Lab and PWD toilet as part of the School of Biomedical Sciences (SBMS) PC2 Laboratory project.

This notification provides a high-level look ahead of works scheduled for the upcoming months. Ongoing communications will be issued throughout the works period to notify users of and around this building any expected disruptive works.

Works on Level 4 Otto Hirschfeld are expected to run from November 2023 to February 2024.

Affected Areas

 

  • Otto Hirschfeld, Level 4, Rooms 402, 405, 406, 408, 409, 410.
  • Otto Hirschfeld, Level 3, Rooms 303 (Cleaner’s cupboard)
  • Otto Hirschfeld, Level 5, Room 518 (Comms riser)
  • Therapies Annexe, Level 3, Room 396 (Lift lobby)

When

  • Start: Monday, 20 November 2023
  • Finish: Friday, 9 February 2024
  • Times: 4am to 4pm

 

Work details

Time

Date

Otto Hirschfeld Building

Demolition

  • Removal of redundant services, fixtures and fittings
    • Hoarding set up around the project site for safety of users, noise & dust control.
    • Services stripped out and made safe.
    • Standard construction noise.

  • Concrete Cutting for new doorway
    • Hoarding set up around the project site for safety of users, noise & dust control.
    • Noisy works with some vibration during concrete cutting.

  • Core holes for drainage
    • Exclusion Zones around work areas on Level 3 of Otto Hirschfeld and Therapies Annexe for safety of users may impact usual pedestrian pathways.
    • Noisy Works during core holing.

  • Floor grinding
    • Noisy Works during floor grinding.

All Day - 7am to 4pm

Early morning 4am to 7:30am

Early morning 4am to 7:30am

Early morning 4am to 7:30am

20/11/23 to 08/01/24

1/12/23 to 1/12/23

23/11/23 to 24/11/23

29/11/23 to 30/11/23

Fitout

  • Mechanical Service
    • Install new AHU
    • Install Mechanical Ductwork

  • Electrical Service
    • Modification to the existing Distribution Board
    • Localised power shutoff to Level 4 is expected for a short period of time.

  • Hydraulic Service
    • Installation of drainage to Otto Hirschfeld, Level 3 ceiling space and Therapies Annexe, Level 3 ceiling space. Exclusion Zones around work areas on Level 3 of Otto Hirschfeld and Therapies Annexe for safety of users may impact usual pedestrian pathways.
    • Connect cold and hot water supply to lab sink and PWD toilet.

  • Partition walls and Joinery
    • Additional details to be provided in the coming weeks.

All Day - 4am to 4pm

All Day - 4am to 4pm

All Day - 4am to 4pm

All Day - 4am to 4pm

1/12/23 to 06/02/24

1/12/23 to 06/02/24

04/12/23 to 05/02/24

1/12/23 to 06/02/24

Commissioning & Testing and Handover

  • Services connection and commissioning
  • Final Clean
  • Inspection
  • Practical Completion

All Day - 4am to 4pm

24/01/24 to 09/02/24

Project details

 

The project aims to transform this area into a specialised PC2 laboratory dedicated to investigating the blood-tissue interface in injury and repair. The construction will include upgrades to existing lab spaces in rooms 405, 406, 408, and 410, along with enhancements to the toilet in room 402 to accommodate an all-gender toilet facility.

Contact

Kevin Park, Project Manager:

We apologise for the inconvenience this may cause and thank you for your understanding during this time.