There will be refurbishment work to Level 4 in Otto Hirschfeld (81) to allow for the delivery of a new PC2 Lab and PWD toilet as part of the School of Biomedical Sciences (SBMS) PC2 Laboratory project.
This notification provides a high-level look ahead of works scheduled for the upcoming months. Ongoing communications will be issued throughout the works period to notify users of and around this building any expected disruptive works.
Works on Level 4 Otto Hirschfeld are expected to run from November 2023 to February 2024.
Affected Areas
- Otto Hirschfeld, Level 4, Rooms 402, 405, 406, 408, 409, 410.
- Otto Hirschfeld, Level 3, Rooms 303 (Cleaner’s cupboard)
- Otto Hirschfeld, Level 5, Room 518 (Comms riser)
- Therapies Annexe, Level 3, Room 396 (Lift lobby)
When
- Start: Monday, 20 November 2023
- Finish: Friday, 9 February 2024
- Times: 4am to 4pm
Work details | Time | Date |
Otto Hirschfeld Building | ||
Demolition
| All Day - 7am to 4pm Early morning 4am to 7:30am Early morning 4am to 7:30am Early morning 4am to 7:30am | 20/11/23 to 08/01/24 1/12/23 to 1/12/23 23/11/23 to 24/11/23 29/11/23 to 30/11/23 |
Fitout
| All Day - 4am to 4pm All Day - 4am to 4pm All Day - 4am to 4pm All Day - 4am to 4pm | 1/12/23 to 06/02/24 1/12/23 to 06/02/24 04/12/23 to 05/02/24 1/12/23 to 06/02/24 |
Commissioning & Testing and Handover
| All Day - 4am to 4pm | 24/01/24 to 09/02/24 |
Project details
The project aims to transform this area into a specialised PC2 laboratory dedicated to investigating the blood-tissue interface in injury and repair. The construction will include upgrades to existing lab spaces in rooms 405, 406, 408, and 410, along with enhancements to the toilet in room 402 to accommodate an all-gender toilet facility.
Contact
Kevin Park, Project Manager:
- Call: 0400 009 276
- Email: k.park1@uq.edu.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.