Please be advised there will be a water shutdown to the following buildings below to allow for the replacement of RPZ devices.
Affected areas
- Banksia (1016), whole building
- Cycad (1018), level 2 all floors
- Elkhorn (1024), level 5 room 522 cooling tower (feeds PC2 labs)
When
Please read below for the schedule
Building | Area | Start | Finish | Times |
Banksia (1016) | Whole building | Thursday 16 March | Thursday 16 March | 12:00pm to 3:00pm |
Cycad (1018) | Level 2, all floors | Thursday 16 March | Thursday 16 March | 6:00am to 9:00am |
Elkhorn (1024) | Level 5 room 522 cooling tower (feeds PC2 labs) | Thursday 16 March | Thursday 16 March | 6:00am to 3:00pm |
Work details
1016 – rpz replacement
1018 – replacement of 32mm RPZ device
1024 – replacement of x2 RPZ devices
Contact
Mitchell Rennie, Axis MS Plumber
- Call: +61 431 177 001
- Email: mitch.rennie@axisms.com.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.