Please be advised, there will be mechanical services works at J.K. Murray Library (8102), Gatton campus as part of a relocation of a chiller plant.
This is an important repurpose of redundant plant that is being transferred to St Lucia Campus for re-use.
Affected areas
- Chiller will be craned from J.K. Murray Library (8102) to the N.W Briton carpark and lifted to trailer for transport off site.
When
- Start: Wednesday, 28 June 2023
- Finish: Wednesday, 28 June 2023
- Times: 6:00am to 4:30pm
Work details
The existing chiller will be lifted by Franna crane to awaiting truck. Franna crane will be operational in and around the N.W. Briton carpark and the plant location adjacent the J.K. Murray Library.
Project details
Union Complex Chiller Replacement- Relocation of Chiller from J.K. Murray library Gatton
Contact
David Muir-McCarey, Project Manager, Infrastructure:
- Call: +61 459 755 432
- Email: d.muirmccarey@uq.edu.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.