The Mansergh Shaw (45) cladding replacement works are continuing with access scaffold being installed and panel removal commencing. The notification below provides a fortnightly lookahead for upcoming works.
This cladding project is expected to run from July 2023 until July 2024
Timeframe: 28 August 2023 to 29 September 2023
Affected Area & Disruption | Time | Date |
North Elevation
Access for deliveries to the loading dock & gas storage area between Mansergh Shaw / Liveris will require communication to the project team. | 06:30am – 05:00pm 06:30am – 05:00pm 06:30am – 05:00pm | Ongoing 29 August 23 – 26 September 23 29 August 23 – 26 September 23 |
West Elevation
| 06:30am – 05:00pm 06:30am – 05:00pm | Ongoing Until 12 September 2023 |
South Elevation
| 06:30am – 05:00pm 06:30am – 05:00pm 06:30am – 05:00pm | Ongoing 29 August 2023 – 12 August 2023 Ongoing |
East Elevation No works during this period. | - | - |
Figure 1: Site Layout Plan:
Figure 2: Site Works Details
Project details
Mansergh Shaw cladding replacement project. Refer to the Façade Replacement Program website for more information.
Contact
Johnny Hegerty, Principal Project Officer:
- Call: 0459 979 518
- Email: j.hegerty@uq.edu.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.