McElwain Building (24A) façade replacement works will commence soon with site fencing and being installed to the northern elevation (Entrance). This notification provides a fortnightly lookahead for upcoming works and will continue to be issued throughout the project. The project is expected to run from Mid-September to Mid-October 2023
Fortnightly Lookahead: 11 September 2023 to 25 September 2023
Affected Area & Disruption | Time | Date |
| 06:30am – 05:00pm | 11/09/23 to 25/09/2023 |
Figure 1: Fence Line
Figure 2: Cladding Removal
Project details
McElwain Building Façade Replacement project. Refer to the Façade Replacement Program website for more information.
Contact
Johnny Hegerty, Principal Project Officer:
- Call: 0459 979 518
- Email: j.hegerty@uq.edu.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.