Facade Replacement Works: UQ Centre (27A) fortnightly lookahead

19 Sep 2023

The UQ Centre (27A) cladding replacement works are ongoing. The below notification provides a fortnightly lookahead for upcoming disruptive works.

This cladding project is expected to run until May 2024.

Timeframe: 18 September 2023 – 29 September 2023

Affected Area & Disruption

Time

Date

Cladding Replacement All Zones

  • Cladding replacement works to continue in all zones from scaffold / EWP.
  • Localised exclusions zones will be in place as required with alternative routes provided.

6:30am – 05:00pm

Ongoing

Entrance to UQ Centre on Union Road

  • Scaffold Build
  • Entry will remain open with an exclusion zone in place near the front entrance during deliveries. Trucks will be parked at the front entry on Union Road when required.
  • Lift to remain open.
  • Noisy works expected during scaffold build.

6:30am – 05:00pm

18/09/23 – 29/09/23

Project details

 

UQ Centre, St Lucia cladding replacement project. Refer to the Façade Replacement Program website for more information.

Contact

Johnny Hegerty, Project Manager:

We apologise for the inconvenience this may cause and thank you for your understanding during this time.