Facade Replacement Works: General Purpose South (78) fortnightly lookahead

16 Nov 2023

The General Purpose South (78) cladding replacement works are ongoing and the notification below provides a fortnightly lookahead for upcoming disruptive works.

This cladding project is expected to run from August 2023 until May 2024.

Lookahead Timeframe: 20 November 2023 – 1 December 2023

Affected Area > Planned Works > Disruption

Time

Date

Northeast Courtyard

  • Cladding measures, removal of panels

600am – 500pm

20 November 2023 - Ongoing

North Middle Courtyard

  • Cladding measures, removal of panels

600am – 500pm

20 November 2023 - Ongoing

Southeast Lakeside

  • Scaffold build progressing and near completion.
    • Exclusion zones in place, including section of lakeside walkway closure.
    • Some Glass Panels will need to be removed and replaced temporarily.

20 November 2023

Figure 1: GP South Works Update Plan

Project details

 

GPS Building, St Lucia cladding replacement project. Refer to the Façade Replacement Program website for more information.

Contact

Johnny Hegerty, Project Officer (Infrastructure):

We apologise for the inconvenience this may cause and thank you for your understanding during this time.

Return to Road and Building works