The UQ Centre (27A) cladding replacement works are ongoing and the notification below provides a fortnightly lookahead for upcoming disruptive works.

This cladding project is expected to run from March 2023 until May 2024.

Lookahead Timeframe: 20 November 2023 – 01 December 2023

Affected Area > Planned Works > Disruption

Time

Date

West (North Union Road)

  • Install new aluminium top hats.
    • Noise from drills/grinders/saws
  • Install new cladding.
    • Noise from drills/grinders/saws
  • Install structural steel to corners.
    • Noise from drills/grinders/saws

West (South Union Road)

  • Remove cladding panels, top hats
    • Noise from drills/grinders/saws

6:30am – 5:00pm

6:30am – 5:00pm

20 November 2023 - Ongoing

Re-commencing January 2024

East Lower

  • Site measure panels and fabricate
    • EWP’s, noise
    • Exclusion zones in place
  • Install new cladding
    • EWP’s, noise
    • Exclusion zones in place

East Upper

  • Install sarking
    • Noise from drills/grinders/saws and EWP’s
    • Exclusion zones in place
  • Install new aluminium top hats
    • Noise from drills/grinders/saws and EWP’s,
    • Exclusion zones in place

6:30am – 5:00pm

6:30am – 5:00pm

20 November 2023 - Ongoing

20 November 2023 - Ongoing

North Elevation

  • Deliveries to hoist
  • Install sarking
    • Noise from drills/grinders/saws
  • Install new aluminium top hats
    • Noise from drills/grinders/saws

6:30am – 5:00pm

20 November 2023 - Ongoing

South Lower

  • Install new aluminium top hats
    • Walkway closed at times to ensure safety of workers and pedestrians
    • Noise from drills/grinders/saws
  • Install cladding 
    • Noise from drills/grinders/saws and EWP’s
    • Exclusion zones in place

6:30am – 5:00pm

20 November 2023 - Ongoing

Roof

  • Remove Solar Panels
    • Noise from walking on roof

6:30am – 5:00pm

22 November 2023 –
6 weeks duration

Figure 1: UQ  Centre Works Update Plan

Project details

 

UQ Centre, St Lucia Cladding Replacement project. Refer to the Façade Replacement Program website for more information.

Contact

Johnny Hegerty, Project Officer (Infrastructure):

We apologise for the inconvenience this may cause and thank you for your understanding during this time.

Return to Road and Building works

Latest