Facade Replacement Works: Hawken Engineering Building (50) fortnightly lookahead

16 Nov 2023

The Hawken Engineering Building (50) cladding replacement works are ongoing and the notification below provides a fortnightly lookahead for upcoming disruptive works.

Lookahead Timeframe: 20 November 2023 – 01 December 2023

Affected Area > Planned Works > Disruption

Time

Date

South

  • Works re-commencing 20 November.
    • Exclusion zones along southern laneway will be in place when EWP is operational, Noise is expected in the form of EWPs.

Access will remain to room S105.

6:30am – 5:00pm

20 November 2023 - Ongoing

North

  • Works re-commencing 20 November.
  • Exclusion zones along southern laneway will be in place when EWP is operational, Noise is expected in the form of EWPs.

6:30am – 5:00pm

20 November 2023 - Ongoing

Figure 1: Hawken Works Update Plan

Project details

 

Hawken, St Lucia Cladding Replacement project. Refer to the Façade Replacement Program website for more information.

Contact

Johnny Hegerty, Project Officer (Infrastructure):

We apologise for the inconvenience this may cause and thank you for your understanding during this time.