The Mansergh Shaw (45) cladding replacement works are ongoing and the notification below provides a fortnightly lookahead for upcoming disruptive works.
Lookahead Timeframe: 20 November 2023 – 1 December 2023
Affected Area > Planned Works > Disruption | Time | Date |
North Elevation
| 6:30am – 5:00pm | 20 November 2023 - Ongoing |
East Elevation
| 6:30am – 5:00pm | 20 November 2023 - Ongoing |
South & West Elevations
| 6:30am – 5:00pm | 20 November 2023 - Ongoing |
Figure 1: Mansergh Shaw Works Update Plan
Project details
Mansergh Shaw, St Lucia Cladding Replacement project. Refer to the Façade Replacement Program website for more information.
Contact
Johnny Hegerty, Project Officer (Infrastructure):
- Call: 0459 979 518
- Email: j.hegerty@uq.edu.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.