Otto Hirschfeld (81) forms part of the UQ Façade Replacement Program. As part of these works the cladding on the Otto Hirschfeld building will be replaced.
This notification provides a high-level look ahead of works scheduled for the coming fortnight. Ongoing communications will be issued throughout the works period to notify users of and around this building of any expected disruptive works.
Works at Otto Hirschfeld Building are expected to run from October 2023 to March 2024.
Forecast Timeframe: 20 November 2023 – 12 January 2024
Time | Date | |
Otto Hirschfeld Building | ||
Main Entry
| All Day - 7am to 5pm | 20/11/23 to 12/01/24 |
Anatomy Entry
| All Day - 7am to 5pm | 20/11/23 to 21/11/23 21/11/23 to 24/11/23 |
Figure 1: Otto Main Entry Exclusion Zone Plan
Figure 2: Affected doorways during Main Entry Works
Figure 3: Otto Exclusion Zones
Work details
St Lucia West Package Cladding Replacement. Refer to the Façade Replacement Program webpage for more information.
Project details
St Lucia (West Package) cladding replacement project.
Contact
Mel Marke, Associate Director (Infrastructure):
- Call: 0429 885 361
- Email: m.marke@uq.edu.au
We apologise for the inconvenience this may cause and thank you for your understanding during this time.