Facade Replacement Works: Building 33 fortnightly lookahead

31 Jul 2023

The Building 33 cladding replacement works have commenced. The notification below provides a fortnightly lookahead for upcoming works.

This cladding project is expected to run from April 2023 until November 2023

Timeframe: 31 July 2023 – 14 August 2023

Affected Area & Disruption

Time

Date

  • Contractor removing cladding and decorative screens, EWP will be used in some areas where screens need to be removed. (Alternative pedestrian routes to be put in place), Noisy works expected.
  • Some disruption to main entrance on Union Road, this will include half of the entrance foyer being closed at any one time as contractor removes cladding.  Elevator and direct building entry access still accessible.
  • Additional site fencing installed along pathway adjacent to union road. (Refer to figure 2 below) Services and club entry doors to be accessible when required. Pathway to remain open.

Note: Access to Brewpoint Café will remain open during normal operating hours. Construction works to commence after 11am.

11:00am – 05:00pm

 31 July 2023 –
14 August 2023

Figure 1 Site Layout Plan:

Figure 2 Site works:

Project details

 

Building 33, St Lucia cladding replacement project. Refer to the Façade Replacement Program website for more information.

Contact

Johnny Hegerty, Principal Project Officer:

We apologise for the inconvenience this may cause and thank you for your understanding during this time.