The General Purpose South (Building 78) cladding replacement works are ongoing and the notification below provides a fortnightly lookahead for upcoming disruptive works.
This cladding project is expected to run until May 2024.
Timeframe: 18 September 2023 – 29 September 2023
Affected Area & Disruption | Time | Date |
North-East Courtyard - Scaffold setup
- Courtyard Exclusion Zones in place until approx. 21st Sep.
- Noisy works expected from drilling into concrete slabs.
- Exclusion zone will shift to next stage of scaffold build (refer North Middle Courtyard section below)
- Level 7 – Concrete Services Scan
- Internal Access required to Level 7 to scan slab for services.
- Hoist install
- Noisy works due to drilling into concrete slab on Level 4 and Level 7 at the eastern end of the building
- Internal Access required to Level 4 and Level 7
- Exclusion Zones – same as existing scaffold exclusion
- Noisy works due to hoist build
|
6:00am – 5:00pm
To be arranged with stakeholder
6:00am – 5:00pm
|
Until 21/9/23
22/9/23
2/10/23 – 6/10/23 |
North Middle Courtyard - The Contractor will be installing two overhead gantries to protect the Level 2 Entry and the Tesla Batteries on the 19th September, refer to Figure 4 for more details.
- No deliveries or pedestrian access to the courtyard during this time.
- Building front entry closed during install. Entry via Level 1 lakeside entry.
- Contractor to commence next stage of scaffold build in the ‘north middle’ area of the courtyard.
- Refer to Figure 3 below to see exclusion zones that will be in place during this scaffold build:
- 25/09/23 – 9/10/23: blue exclusion zone. Skip bin will be temporarily moved.
- 9/10/23 – 23/10/23: yellow exclusion zone. No access to courtyard unless pre-arranged. Access for emergency egress only.
- Noisy Works due to scaffold erection
- Level 2 building entry may need to be closed intermittently during scaffold build.
|
6:00am – 5:00pm
6:00am – 5:00pm
|
19/9/23
25/9/23 – 23/10/23
|
Figure 1: Site Layout Plan
![](/files/29885/23-9-19%20GPS%203.jpg)
Figure 2: Site Compound Permanent Set-Up Following Scaffold Build
![A aerial view of a building with solar panelsDescription automatically generated](/files/29875/23-9-19%20GPS%202.jpg)
Figure 3: Courtyard Closure for Scaffold Build – Stage 2
![](/files/29885/23-9-19%20GPS%203.jpg)
Figure 4: Level 2 Entry Closure for Gantry Build
![](/files/29895/23-9-19%20GPS%204.jpg)
Project details
General Purpose South (78), St Lucia cladding replacement project. Refer to the Façade Replacement Program website for more information.
Contact
Johnny Hegerty, Project Manager:
Casey Fredrickson, Project Manager: