This announcement includes updates for the following works:
- PACE (870) Façade Replacement
- Construction of the Translational Manufacturing facility at the Translational Research Institute (TM@TRI)
Please note that TM@TRI works are adjacent to the Pharmacy Australia Centre for Excellence (870) on UQ-owned land but are otherwise separate to the works currently underway at PACE.
PACE Façade Replacement
Some disruption to the Pharmacy Australia Centre of Excellence (PACE) Building 870 for the Façade Replacement Project will continue as the contractor progresses with the replacement of the noncompliant combustible cladding scope of work. These works will cause some intermittent noise and there will be some exclusion zones to footpaths, roads and work zones during these works, managed by the Contractor.
The cladding replacement on the PACE Building is expected to be complete by January 2024. Ongoing communications will be provided to give regular updates regarding upcoming works.
Affected Areas | Duration & Time |
Site Operations / Site Establishment
| Ongoing |
Lecture Theatre
| 3 July – 21 July |
Level 6 Glazing
| 11 July – 21 July
10 July – 14 July |
Please refer to attached PDFs for affected area markup (PDF, 5.4 MB) and monthly lookahead (PDF, 447.3 KB).
Project details
Cladding replacement on the PACE Building forms part of the wider UQ Façade Replacement Program.
PACE Façade Works Contact
Casey Fredrickson, Senior Project Manager (Infrastructure):
- Call: 0408 339 936
- Email: c.fredrickson@uq.edu.au
TM@TRI Construction
Early works on the TM@TRI site will commence Monday 10 July 2023. See attached PDFs for further details (PDF, 170.4 KB) and 6-week lookahead (PDF, 4 MB).
TM@TRI Contact
If you have any enquiries relating to works at TRI, contact the TRI project team:
We apologise for the inconvenience this may cause and thank you for your understanding during this time.